When buying fabricated steel for a warehouse or industrial building, agree on the inspection and test plan (ITP) before fabrication. For each stage, identify who checks the work, what they check against, what record they issue and whether work can proceed without buyer or third-party sign-off.
Make the inspection scope part of the purchase order or its attachments, especially when quotations include different levels of inspection. This gives the fabricator and the inspection agency time to allow for visits, testing and release in their schedules.
Agree on inspection responsibilities before placing the order
- List the applicable drawing revisions, project specifications and acceptance criteria. Define the inspection method and the scope or sampling for each stage, including which pieces or welds require testing.
- Identify who performs the fabricator’s quality control, who carries out owner or third-party quality assurance when specified and who may approve release. State who arranges and pays for any independent visit, testing and reinspection.
- Define the notification lead time, what happens if a witness cannot attend and whose written authorization is required to clear a hold point. Under AISC projects using ANSI/AISC 303-22, Section 8.1.3 addresses documenting the scope of additional or independent inspection.
Example inspection and test plan for a warehouse frame
Use these rows as a starting point. Set the applicable limits, sampling, timing and sign-off in the project documents. The example assumes a painted steel frame.
| Stage | What to verify | Evidence to request |
|---|---|---|
| Steel receipt | Match grade and heat identification to the material list and the traceability procedure. | Mill test reports and a material register linking heats to member marks where required. |
| Fit-up and fabrication | Check joint preparation, dimensions and hole patterns against the current shop drawings at the stages specified in the plan. | Fit-up and dimensional inspection reports identifying the pieces or lots checked. |
| Welding before coating | Complete visual inspection and any specified nondestructive testing (NDT) while the welds are accessible. Record required reinspection after repairs. | Weld inspection records, applicable NDT reports and disposition of any rejected welds. |
| Surface treatment and coating | Check surface preparation and the specified coating system. Measure dry film thickness where the specification requires it. | Surface preparation and coating inspection records with the relevant piece or batch identifiers. |
| Shipment release | Match member marks and quantities to packing lists, then verify that any applicable holds are cleared before loading. | Packing list by shipment, completed inspection records and the agreed release authorization. |
Review the release records before loading
- Trace one or more member marks from the packing list back to the inspection reports and the applicable drawing revision. Agree on how to handle split shipments and records covering several lots.
- Check that each nonconformance affecting the shipment has been closed or has an approved written disposition from the responsible party. Link any repair or reinspection record to the affected pieces.
- Confirm whether release is by lot or by shipment and who signs it. Keep shop release separate from any site receiving checks and final acceptance defined in the contract.
References
This guide describes general practice. Project requirements must be confirmed with the responsible project team before fabrication.