Project Case

Building Materials Factory Workshops

Steel structure works for three factory workshop buildings at a building materials production site, with a combined floor area of 12,876 m2.

Steel workshop frame during roof construction

Confirmed case facts

What is confirmed for this project

These figures were provided by the company for this project. The client name is not published.

Location
Fugou County, Zhoukou, Henan Province, China
Building type
Factory workshop buildings
Scope size
Three workshop buildings
Floor area
12,876 m2 in total
Steel tonnage
Approximately 410 tons
Delivery period
May 2023 to December 2023, about seven months
Steel workshop frame during roof construction

Fabrication scope

What the steel structure package covered

  • Primary steel frame and secondary members for three workshop buildings
  • Fabrication to the approved shop drawings, including welding and dimensional inspection
  • Surface preparation and coating before packing
  • Bundling, marking to the packing list and delivery to the project site

The photograph illustrates this building type. It is not a photograph of this project.

Standard route

How a project like this moves through the factory

The sequence below is the standard fabrication route. The specific inspection scope and standards are confirmed for each project.

  1. 01

    Raw material receiving

    Material identity, dimensions and documentation are checked against confirmed project requirements.

  2. 02

    Cutting

    Approved member information guides plate and section preparation.

  3. 03

    Assembly

    Components are fitted and checked against approved fabrication information.

  4. 04

    Welding

    Welding requirements and inspection scope follow confirmed project documentation.

  5. 05

    Straightening

    Member geometry is checked and corrected within the confirmed acceptance criteria.

  6. 06

    Shot blasting

    Surface preparation requirements must be confirmed before processing.

  7. 07

    Painting

    Coating system, color, dry-film requirements and repair method require project confirmation.

  8. 08

    Packing and loading

    Marks, bundles, protection and loading sequence are reviewed before shipment release.

Quality control

Checkpoints recorded before release

These are the control points applied before a member or bundle is released.

  1. 01

    Material receiving check

    Steel grade, heat number and mill test certificates are checked against the approved material list before any plate or section is cut.

  2. 02

    Cutting and drilling check

    Component length, hole diameter, hole group position and edge preparation are measured against the approved shop drawings.

  3. 03

    Assembly and welding check

    Fit-up, root gap, camber and weld leg size are checked before welding. Weld procedures and welder qualification follow the standard specified for the project.

  4. 04

    Dimensional inspection

    Overall length, squareness, member straightness, connection locations and hole groups are measured after welding and before surface treatment.

  5. 05

    Surface treatment check

    Shot-blast grade, coating dry film thickness or galvanizing coverage are inspected and recorded against the coating specification.

  6. 06

    Packing inspection

    Bundle contents, piece marks, protection of connection faces and the loose-part list are checked against the packing list before loading.

Packing and delivery

How the shipment side is prepared

Packing, marking and loading preparation follow the same sequence for every order.

01

Bundling

Members are bundled by type and length, with bundle weights and lifting points recorded so the container plan and site crane capacity match the load.

02

Marking

Every bundle carries a piece mark, bundle number and project reference that match the packing list and the erection drawings.

03

Protection

Connection faces, machined surfaces, coated edges and insulated panels are protected for sea freight. Loose parts are packed and itemised separately.

04

Container Loading

Loading plans use 40HQ, 40OT or 20GP containers, with the sequence set by component weight, length and the unloading order at site.

Related cases

Other confirmed project records

Xiangcheng, Henan Province, China

Logistics Park Warehouse Buildings

Steel structure works for five warehouse buildings in a logistics and distribution park, fabricated and delivered as one package.

Floor area
30,000 m2 in total
Steel tonnage
Approximately 900 tons
View Case

Luohe, Henan Province, China

Cotton Storage Warehouse Project

Eight cotton storage warehouses, covering steel structure fabrication and installation, with a combined floor area of 15,448 m2.

Floor area
15,448 m2 in total
Steel tonnage
Approximately 742 tons